Time and Work - Mathematics (SSC CGL CHSL)

Using Ratio Method

Using Ratio Method — M₁W₁T₁ = M₂W₂T₂

This equation is based on the principle that: Total Work Done = Number of Workers × Work Units per Day × Time

In competitive exams like SSC CGL and CHSL, this formula is super useful when we deal with two scenarios or two different teams working under different conditions.

M₁W₁T₁ = M₂W₂T₂
Where:
M = Number of Men (or any worker)
W = Work per Day (Efficiency per worker)
T = Time in Days


Example 1: Direct Application (Same Work Type)

Q: 5 men can complete a work in 12 days. How many days will 6 men take to complete the same work?

Solution:
Using ratio method: \[ M₁T₁ = M₂T₂ \Rightarrow 5 \times 12 = 6 \times T₂ \Rightarrow T₂ = \frac{60}{6} = 10 \text{ days} \]

Answer: 10 days


Example 2: Mixed Workers Without Converting

Q: 4 men and 6 women can do a work in 8 days. How many days will 6 men and 4 women take to do the same work, if their efficiencies are in ratio 3:2?

Step 1: Use ratio instead of converting

Let man’s efficiency = 3, woman’s = 2

Step 2: Apply formula using weighted efficiencies

Left side = (4×3 + 6×2) × 8 = (12 + 12) × 8 = 24 × 8 = 192 Right side = (6×3 + 4×2) × T₂ = (18 + 8) × T₂ = 26 × T₂

\[ 192 = 26 × T₂ \Rightarrow T₂ = \frac{192}{26} = 7.38 \text{ days (approx)} \]

Answer: 7.38 days


Example 3: Men, Women, and Children Together

Q: 3 men, 5 women, and 2 children can complete a work in 10 days. In how many days will 4 men, 4 women, and 4 children do the same work? Efficiencies are: Man : Woman : Child = 6 : 4 : 2

Step 1: Weighted workers

Total work by first group per day = 3×6 + 5×4 + 2×2 = 18 + 20 + 4 = 42 units Total work = 42 × 10 = 420 units

Step 2: Efficiency of second group

4×6 + 4×4 + 4×2 = 24 + 16 + 8 = 48 units/day Time = 420 / 48 = 8.75 days

Answer: 8.75 days


Example 4: Ratio Method When Some Leave the Job

Q: 8 men can do a job in 15 days. They work for 6 days, and then 2 men leave. In how many more days will the remaining work be completed?

Step 1: Total Work = 8×15 = 120 man-days
Step 2: Work done in first 6 days

8 × 6 = 48 man-days Remaining = 120 − 48 = 72 man-days

Step 3: Remaining work done by 6 men

T = 72 / 6 = 12 days

Answer: 12 more days


Example 5: Ratio Method in Reverse — Find Number of Workers

Q: 6 men can do a work in 16 days. How many men are needed to do it in 12 days?

Apply ratio:
\[ M₁T₁ = M₂T₂ \Rightarrow 6 × 16 = M₂ × 12 \Rightarrow M₂ = \frac{96}{12} = 8 \]

Answer: 8 men

Tips for Ratio Method

  • Don’t convert into one worker — use their efficiency ratio directly.
  • Calculate total efficiency of each group (multiply number × efficiency).
  • Then apply: Total Work = Group Efficiency × Time
  • Or set: (E₁ × T₁) = (E₂ × T₂) when work is constant
Summary
Scenario Approach
Different groups, same work Use M₁W₁T₁ = M₂W₂T₂
Mixed worker types Assign ratios, use group efficiency
Joining/leaving midway Break into parts before and after